Task: Powerco-Tenix contracted LMS to undertake an as-built hydrographic survey of the under-sea cable from Tairua to Pauanui.
The survey was conducted using RTK GPS with lead-line soundings taken to obtain a seabed profile along the alignment of the as-laid cable. The equipment & personnel were deployed aboard a small vessel hired from Discovery Marine Limited – Mt Maunganui
The cable-laying contractor had previously marked the cable alignment with buoys (plastic bottles) attached to tethers that were tied to the cable during the laying phase.
In places the cable and trench were still visible in water depths up to 4m. The cable was trenched to an approximate depth of 1m below the seabed.